Which article of A1A A201 defines procedures for handling changes to the work, including when there is disagreement?

Get more with Examzify Plus

Remove ads, unlock favorites, save progress, and access premium tools across devices.

FavoritesSave progressAd-free
From $9.99Learn more

Prepare for the NICET Level 3 Fire Alarm Systems Exam. Study with comprehensive flashcards and detailed multiple choice questions, each offering insights and explanations. Excel in your certification journey!

Article 7 of AIA A201 is indeed the section that outlines the procedures for handling changes to the work, particularly regarding contract modifications, adjustments in contract sum or time, and the protocols to follow when disagreements arise. It sets forth the process for change orders and how unforeseen circumstances or alterations initiated by the owner can be addressed.

This article provides key insights into the documentation required for changes, the need for written agreements, and how disputes around changes can be resolved. Understanding this section is crucial for managing the contract effectively and ensuring that both parties are aligned on modifications, thus maintaining clear communication and documentation to prevent potential disputes.