What article of AIA A201 assigns responsibility for the correction of defective and nonconforming work?

Get more with Examzify Plus

Remove ads, unlock favorites, save progress, and access premium tools across devices.

FavoritesSave progressAd-free
From $9.99Learn more

Prepare for the NICET Level 3 Fire Alarm Systems Exam. Study with comprehensive flashcards and detailed multiple choice questions, each offering insights and explanations. Excel in your certification journey!

Article 12 of the AIA A201 addresses the responsibilities of the contractor regarding the correction of defective and nonconforming work. This article outlines that the contractor is responsible for repairing or replacing any work that does not conform to the contract documents. Additionally, if there are defects identified, the contractor is required to remedy those issues at their own expense, ensuring compliance with project specifications and quality standards.

By specifying these responsibilities, Article 12 ensures that the integrity of the construction project is maintained and provides a clear framework for addressing issues that may arise during the construction process. This helps protect the interests of the owner and maintains a standard of excellence within the completed work.